Abstract

This paper presented a method for simultaneous clearing of energy and storage markets. The proposed method pursued two goals. The first goal was to take into account the random changes in production in the power grid, for which a random clearing model and the Monte Carlo method were used. In the second goal, the economic operation of production units and their reliability in the process of allocating the required capacity of the energy market and storage to generators, was considered. In the relevant objective function, in addition to energy supply and storage costs, non-energy delivery and storage costs were also included. The outputs of the proposed method could be used in the process of creating the necessary incentives among manufacturers. Because the more reliable the manufacturer, the more market share it would have. The efficiency of the proposed method on a sample network was evaluated and the results are presented.

References

Adebisi OI, Adejumobi IA. Development of a load management scheme for the Nigerian deregulated electricity market using regression model. IEEE PES/IAS Power Africa. 2019:682-687.

Scheduling operations manual. Pennsylvania - New Jersey - Maryland (PJM) Interconnection. Available at the URL: http://www.pjm.com.

Market operations. Independent System Operator (ISO). New England. Available at the URL: http://www.iso-ne.com.

CAISO 28-Jun MD02 tariff filing of clean tariff sheets and errata. Available at the URL: http://www.caiso.com.

Najafi M, Ehsan M, Fotuhi-Firuzabad M, Akhavein A, Afshar K. Optimal reserve capacity allocation with consideration of customer reliability requirements. Energy. 2010;35:3883-3890.

Banshwar A, Sharma NK, Sood YR, Shrivastava R. A sequential optimization approach for competitive procurement of energy and ancillary services. International Conference on Electrical Power and Energy Systems. 2016:498-503.

Aminifar F, Fotuhi-Firuzabad M, Shahidehpour M. Unit commitment with probabilistic spinning reserve and interruptible load considerations. IEEE Transactions on Power Systems. 2009;24:388-397.

Shi K, Chen H, Li P, Wang X, Liu Y, Sun G. Analysis of two electricity market clearing mechanisms based on co-evolution [J]. Automation of Electric Power Systems. 2019;43:68-77.

Huang L, Chen H. Simulation and analysis of centralized bidding market clearing method based on intelligent algorithm. IEEE Innovative Smart Grid Technologies-Asia. 2019:2963-2967.

Wang J, Wei Z, Yang B, Yong Y, Xue M, Sun G, Zang H, Chen S. Two-stage integrated electricity and heat market clearing with energy stations. IEEE Access. 2019;7:44928-44938.

Yu CW, Zhao XS, Wen FS, Chung CY, Chung TS, Huang MX. Pricing and procurement of operating reserves in competitive pool-based electricity markets. Electric Power Systems Research. 2005;73:37-43.

Allan RN. Reliability evaluation of power systems. Springer Science & Business Media. 2013.

Wu L, Shahidehpour M, Li T. Cost of reliability analysis based on stochastic unit commitment. IEEE Transactions on Power Systems. 2008;23:1364-1374.

Mok YL, Chung TS. Prediction of domestic, industrial and commercial interruption costs by relational approach. International Conference on Advances in Power System Control, Operation and Management.1997;450:209-215.

Yang D, Sun Y, Li B, Zhang X, Li P, Zhang T. Design of long-term and medium-term trading model under multi-energy coupling. IOP Conference Series: Earth and Environmental Science 2019;371:052052.

Bhattacharya K, Bollen MH, Daalder JE. Real time optimal interruptible tariff mechanism incorporating utility-customer interactions. IEEE Transactions on Power Systems. 2000;15:700-706.

Jingyi S, Xin J, Jinfeng G, Haoyong C, Ke S. Experimental analysis of equilibrium of long-term market clearing mechanism in China. IEEE Innovative Smart Grid Technologies-Asia. 2019:2986-2990.

Hillier FS. Introduction to operations research. Tata McGraw-Hill Education. 2012.

Bussieck MR, Meeraus A. General algebraic modeling system (GAMS). Modeling Languages in Mathematical Optimization 2004:137-157.

Downloads

Published

2021-03-30

How to Cite

Amouzad Mahdiraji, E., & Sedghi Amiri, M. (2021). Market Clearing due to the Reliability of Electricity Generation Units. Advanced Journal of Science and Engineering, 2(1), 42–50. https://doi.org/10.22034/advjscieng21021042

Issue

Section

Original Research Article